The Grove: construction site update
JANUARY 2021
Progress report:
80% of Sewage drainage Pipelines and Manholes – Achieved
80% of Water drainage Pipelines and Manholes – Achieved
80% construction of water hydrants – Achieved
100% Road Excavation- Completed
90% Rock Blasts and Moved to various plots for Structural integration – Achieved
60% of Laterite filling and road construction for all roads; Road 1 -11 – Achieved